By the
beginning of next year, California will have a new governor and perhaps a new
perspective on its largest building project of this and the next decade – the
fractionally-built and ultra-controversial bullet train now under construction
in Madera and Fresno counties.
A new
governor can mean a new board of directors for the High Speed Rail Authority
and a new outlook on the current management’s biggest error – its insistence on
routing the new train through the most populated parts of the Central Valley
rather than along the much more open route of Interstate 5 on that valley’s
western edge.
It’s
not often that a state agency can reverse course, give up on a mistake and
still give Californians something they would need and use. But this is such an
opportunity.
There
are many reasons the bullet train project, whose almost $10 billion in state
bonding authority was OK’d at the polls 10 years ago, has lost much of its
support, with fewer than half the voters polled early this year supporting its
continuance.
But a
need for fast ground transportation between Northern and Southern California
remains. Anyone who has fought traffic at the main airports of the Los Angeles
and San Francisco areas knows congestion there grows steadily, making flying
far more difficult than it was a few years ago.
The
obvious solution from the beginning was to route high speed trains along the
state’s most traveled and shortest north-south route, Interstate 5. That route
has very wide medians for much of the distance between Grapevine at the
northern foot of the Tehachapi Mountains and either the California 152 highway
west over Pacheco Pass to Gilroy and the Silicon Valley or the Altamont Pass
east of Livermore and the East Bay suburbs of San Francisco.
But
High Speed Rail Authority members appointed first by ex-Gov. Arnold Schwarzenegger
and later by current, but outgoing, Gov. Jerry Brown wouldn’t hear of this.
Instead, they opted to send the bullet train through Bakersfield, Fresno,
Madera and Merced before heading it west along the 152.
That
choice spurred myriad lawsuits from farmers and other landowners whose
livelihoods could be disrupted by the train’s tracks and viaducts. It led to
fierce opposition from San Joaquin Valley Republicans in Congress backing their
supporters in agriculture.
It has caused delays of half a
decade or so in the project’s predicted completion date and contributes heavily
to cost overruns forecast to double the original $35 billion cost estimate.
This forecast comes from the rail authority’s own latest business plan, which
also has cut expected speeds far below the originally promised 220 mph for much
of the current route.
Imagine how many more
lawsuits, delays and cost overruns the bullet train will encounter when and if
construction reaches the San Francisco Peninsula, where Silicon Valley’s
massive wealth could be arrayed against it.
There’s
also the issue of whether intermediate stops in cities like Fresno and Merced
are worth having. The experience of Europe’s Paris-to-Amsterdam Thalys bullet
train is instructive here. That line stops at major cities like Brussels and
Rotterdam, but almost no one enters or exits there. Almost all riders stay aboard for the full
run.
If
stops in much larger cities are barely used during a European run of almost the
same distance as Los Angeles to San Francisco, why believe many will use
stations in the smaller California cities?
The
latest official cost and speed estimates for the California train have plainly
put this project in peril. There’s a strong risk the bridges and viaducts
already built will someday be monuments to a huge failure.
Better
to abandon them now, before investing billions of dollars in even more
prospective white elephants, and switch to a far saner, cheaper and less
disruptive route up I-5 and over the Altamont Pass to Livermore, where
passengers could easily switch to new high-speed Bay Area Rapid Transit trains
for the rest of the ride into San Francisco.
The
time and money saved would be phenomenal, even if some politicians and their
appointees would lose face in the process.
-30-
Email Thomas Elias at tdelias@aol.com. His book, "The Burzynski Breakthrough: The Most Promising Cancer Treatment and the Government’s Campaign to Squelch It," is now available in a soft cover fourth edition. For more Elias columns, go to www.californiafocus.net
Email Thomas Elias at tdelias@aol.com. His book, "The Burzynski Breakthrough: The Most Promising Cancer Treatment and the Government’s Campaign to Squelch It," is now available in a soft cover fourth edition. For more Elias columns, go to www.californiafocus.net
No comments:
Post a Comment